2 Bedroom Bungalow -ID 2111
Build cost KSh 2,979,015
2 Bedroom
1 Bathroom
40x80 and above
A great cost effective design where budget needs to be considered.
Floor Plans
Materials | Labour | |
---|---|---|
Excavations | KSh 0 | KSh 9,000 |
Foundations and hardcore filling | KSh 186,796 | KSh 40,600 |
Ground floor slab | KSh 107,278 | KSh 49,000 |
Walling | KSh 116,999 | KSh 31,400 |
Roof beam | KSh 97,769 | KSh 12,000 |
Roofing | KSh 0 | KSh 0 |
Plasterwork, floor screeds and window cills | KSh 61,088 | KSh 20,400 |
Windows | KSh 45,900 | KSh 8,800 |
Doors | KSh 68,600 | KSh 8,800 |
Tiling | KSh 94,984 | KSh 8,800 |
Kitchen, wardrobes, store shelving and mirrors | KSh 168,745 | KSh 0 |
Wiring, sockets, switched and bulb holders | KSh 29,642 | KSh 5,600 |
Toilets, showers, water tanks and sinks | KSh 134,050 | KSh 5,600 |
Paintwork | KSh 87,904 | KSh 11,000 |
Waste water disposal | KSh 167,400 | KSh 23,800 |
Parking slots | KSh 0 | KSh 0 |
Elecrical works(see separate document for illustration) | KSh 3,090 | KSh 3,200 |
KSh 0 | KSh 2,400 | |
Plumbing and drainage(see separate document for illustration) | KSh 37,230 | KSh 5,600 |
Plumbing and drainage(see separate document for illustration) | KSh 18,785 | KSh 5,600 |
Roof structure and roof covering | KSh 753,776 | KSh 156,800 |
Ceiling finishes | KSh 101,520 | KSh 26,600 |
Fascia board | KSh 9,933 | KSh 6,600 |
Rain water pipes and gutters | KSh 20,902 | KSh 4,400 |
Plumbing and drainage(see separate document for illustration) | KSh 212,390 | KSh 5,600 |
Elecrical works(see separate document for illustration) | KSh 10,880 | KSh 9,200 |
Plumbing and drainage(see separate document for illustration) | KSh 4,480 | KSh 6,600 |
Concrete plinth: | KSh 4,547 | KSh 0 |
Concrete tops: | KSh 2,315 | KSh 22,800 |
Elecrical works(see separate document for illustration) | KSh 11,950 | KSh 5,600 |
Excavations | KSh 0 | KSh 12,000 |
Materials | KSh 144,288 | KSh 20,400 |
When you buy this plan you'll get;
- Architectural drawings in PDF format
- Bills of materials and labour with budget costs
- Access to a project management tool to help you manage your build
- All engineering drawings
- Access to Inuua verified suppliers and contractors